Measure Again

in #disaster7 years ago

This is a re-measurement of project activities that have been done more than 50%, on this occasion we as the project implementer filed several complaints related to the construction that we can not finish in accordance with the initial planning because there are differences in assumptions between the results of initial measurements with real conditions in the field.

IMG-20170710-WA0011.jpg

This activity should be carried out by us as executors in the field together with field supervisor consultants and accompanied by Supervisors from relevant offices.

IMG-20170710-WA0010.jpg

After the completion of all these measurement activities are finally found a new volume that must be done by us as the executor of this work. Furthermore, together with our supervisory consultants direct the executor of the field in the form of heavy equipment in order to carry out further activities in accordance with the volume that has been generated from this repeat measurement.

IMG-20170710-WA0009.jpg

Sort:  

steady, the spirit of bang, hopefully what is in the plan will go smoothly .. whatever the obstacle. the important spirit, with the spirit, the complex so light ..

Thank you luxman for making a transfer to me for an upvote of 2.30% on this post!

funds growth projects for Steem like our top 25 posts on Steem!Half of your bid goes to @budgets which

The other half helps holders of Steem power earn about 60% APR on a delegation to me!

For help, will you please visit https://jerrybanfield.com/contact/ because I check my discord server daily?

To learn more about Steem, will you please use http://steem.guide/ because this URL forwards to my most recently updated complete Steem tutorial?

Meunyoe jeut neu cor laju nyan, bek jeut longsor, peng jih pake ata hinan aju siat