RCC drawings so that you can find out the following values from the drawing :
Once Again We Have Revised It Before Start Work.....
A Well Engineer Must Know This...
Length of the element :
Cross section:
No of bars
Type of bars
Spacing between the bars.
Lap length ( horizontal/vertical)
Development length
Covers for footing/column/beam/slab.
and Important One Formula Here For A Civil Engineer
Slab Reinforcement
- Calculate the cutting length of the bars.
( total length – covers on bothside )+ development length.
3.Formula :
W = NCLU
W: Weight of reinforcement
N: No of bars
CL: cutting length
U:Unit weight
You can find out Unit weight from charts or from the formula :
U= D*D/162.
Must Have to Know About This Formula..
Yes, sometimes have to check the steel on site when I do that type of contract...